wholesale china electronicSewage pressure pipe by drilling and blasting in large amounts of sewage i

The new bulletin news reporter Xie Yuanyuan Zhang Xiaodan reported yesterday,wholesale china electronic, a reporter from the Guangzhou municipal sewage treatment company was informed that, 26 days afternoon 2 when, Pan Tong Bay Shangjie Liwan sewage lifting pumping station DN1200 outlet pressure pipe by drilling and blasting, a large amount of wastewater emission into the Pearl River road.
As of five pm yesterday, flows into the Pearl River sewage gets basically controlling, Lichee Bay Bay yet affected, Sima poured water and slightly affected.City sewage treatment company said, damaged sewer quickly acquired the completion of repair.
After the accident, the provincial Party committee, party secretary Zhang Guangning pays close attention to very much and make written instructions, deputy secretary of Municipal Committee, mayor Wan Qingliang and the Municipal Standing Committee, executive vice mayor Su Zequn after receiving the report of pipe burst handling instructions, "organizational strength fully repair, return to normal as soon as possible".
It is reported, the incident of sewage pressure pipe is Guangzhou City Hengsheng Construction Engineering Company Limited drilling and blasting, the company is integrated punish road Lichee Bay reinforcement engineering construction.
After receiving the report, the city sewage treatment company quickly start should be urgently plan, to drill breaking point road around were enclosed, and suspend the Australian export sewage pumping station and sewage pumping station in Liwan,china electronics wholesale and dropship, strengthen the relevant river gate station scheduling, maximum limit reduces the sewage overflow on the river and Pearl River's influence.
According to introducing, crash in Lichee Bay into the Pearl River Estuary, water will not flow into the Lichee Bay Bay, but due to pumping station outage, Lichee Bay Bay's water quality will be affected.
Yesterday morning, repair units sent divers into the drilling and blasting point sewage pipeline survey, proved the sewage pipeline breakage is a 1 m long, 1 cm wide cracks and a lead hole construction.
At present, city sewage treatment public company has initially developed a repair program, repair equipment and emergency personnel are in place, is to carry out repair work.But because of the burst and leakage pipeline is located in edge, pipeline buried deeper, and located in the quicksand layer, affected by the tide in the Pearl River greatly, repair of complex environment, it is quite difficult to repair.
It is understood, can be the fastest in November 30th 8 before the completion of the repair work.City sewage treatment company also called for the construction unit to strengthen construction management, put an end to the barbaric construction, love city sewage pipe network, maintenance of city water environment.